What makes an advanced-packaging RFQ useful?
Send a process-zone brief, coordinated interface drawings and an acceptance register with your panel quantities. For outsourced semiconductor assembly and test (OSAT), these records help suppliers quote the same enclosure scope while identifying decisions that remain with the process owner, equipment supplier or engineering team.
This checklist concerns semiconductor cleanroom wall panels, ceilings, doors and openings. It does not specify production tools or assign a universal room class. Use it alongside the semiconductor enclosure guide and general quotation checklist.
Complete the fields below and download each CSV before leaving. Entries stay in this tab and are not submitted. On a narrow screen, scroll each register sideways. The blank prompts are procurement aids, not project specifications or records of completed AILV work.
1. Map each exposed process
Identify the actual sequence: for example, dicing, die attach, bonding, encapsulation or test. Mark when the product surface is exposed, what carries it, and where it moves between equipment and rooms. Add the relevant cleaning and maintenance activities.
Record whether protection belongs to the room or a local equipment environment. ISO 14644-7 addresses separative devices but leaves application requirements to the customer and supplier. The process owner must therefore supply the relevant limits; an “advanced packaging” label is not that brief.

| Zone / record | Process and exposure | Environment boundary | Requirement owner |
|---|---|---|---|
| P-01 | |||
| P-02 |
2. Name the interface owners
Request the selected tool supplier’s facilities data, equipment envelope and connection drawings. SEMI F122’s public scope covers facilities data and equipment interconnections through installation and hook-up. Use the project-adopted documentation requirements; this register is not a SEMI compliance certificate.
Put panel, ceiling, access and service interfaces on the same drawing revision. Name who designs, supplies, installs and checks each interface. A shared line on two drawings needs an agreed owner, including supports, seals and access for later maintenance. Coordinate ceiling openings and supports separately.

| Interface | Coordinated input | Design / installation owner | Approval / status |
|---|---|---|---|
| Tool entry / removal | |||
| Ceiling / airflow | |||
| Services / seals |
3. Agree the evidence before ordering
For each requirement, identify the applicable zone or construction, acceptance method, evidence and reviewer. ISO 14644-1 concerns airborne-particle classification. Record chemical or electrostatic requirements separately; the EOS/ESD Association describes ESD control as a coordinated program.
For a retrofit, list retained equipment, isolation boundaries and available access periods. ISO 14644-4 spans requirements through start-up, including modified installations. The project team should agree its verification and release sequence before the enclosure package is ordered.

| Item | Agreed requirement / method | Evidence / revision | Reviewer / status |
|---|---|---|---|
| Room environment | |||
| Panel construction | |||
| Installed interface |
Match material or test documents to the offered facing, core, thickness, edge and assembly. Keep an unresolved item marked open rather than treating a generic brochure as acceptance evidence. See the interactive junction references when discussing connections.
AILV manufactures enclosure products. K-STONE provides sales and engineering support within the agreed scope. Send the registers with layouts, quantities and destination; identify specialist equipment, HVAC, ESD, qualification and site-work responsibilities separately.
The linked official sources support the distinctions above. Their public scopes were checked on 2 November 2026; no paid standard text is reproduced. The registers are original procurement aids and do not replace the project specification.
Advanced-packaging enclosure FAQ
Does advanced packaging automatically require ISO 4–6?
No universal class is assigned here. Ask the process owner to define the required room and local environments, particle sizes and operating states. Packaging technology names or a nominal panel thickness do not establish those requirements.
Does a room particle class prove ESD performance?
No. Particle classification and electrostatic control address different properties. Specify the relevant surface, grounding and verification requirements within the project ESD program; match any panel evidence to the actual offered construction.
Can AILV review an RFQ before every field is complete?
Yes. Send the available layout and registers, mark unresolved fields and identify who will confirm them. A preliminary enclosure proposal must retain its assumptions and exclusions until drawings, materials, quantities and responsibilities are agreed.