Jiangsu Beverage-Filling Cleanroom Project

Jiangsu Beverage-Filling Cleanroom Project

A 2,500 m² Jiangsu beverage-filling cleanroom completed in 2023, with AILV responsible for design, on-site installation and system commissioning.

This 2,500 m² beverage-filling cleanroom project in Jiangsu, China, completed in 2023, shows how production equipment, access platforms and overhead services occupy the room together. Stainless vessels and connected pipework sit within a finished enclosure, with lighting and ceiling interfaces visible above the process area. AILV was responsible for design, on-site installation and system commissioning.

Location
Jiangsu, China
Industry
Beverage filling
Project area
2,500 m²
Completed
2023

Delivery Responsibilities & Handover

Project stage Responsible party
Design AILV
On-site installation AILV
System commissioning AILV

Confirmed Handover Record Types

  • As-built drawings
  • Equipment documentation
  • Installation inspection records
  • System commissioning or test reports

Project Context

The close relationship between equipment and pipe routes makes interface planning important. Production access, cleaning activities and maintenance need to be considered alongside the locations of structural supports, valves and service connections.

Engineering Interfaces to Review

  • Review the equipment arrangement and operator routes before setting room boundaries. Confirm installation access and the clearances needed around vessels, platforms and filling-area equipment.
  • Coordinate overhead pipework with ceiling modules, lighting and ventilation outlets. Agree support details, inspection access and the responsibility for each service penetration.
  • Use the actual cleaning regime to review exposed surfaces and junctions. Define the utility, drainage and equipment-connection requirements with the selected process-equipment suppliers.

Project Photo Album

Plan a Similar Project

For a similar beverage facility, provide the production flow, equipment schedule, utility and cleaning requirements, room drawings and the requested engineering and installation scope.

Explore related engineering solutions · Review project and EPC responsibilities · Discuss your project with AILV

For a food line with a different process layout, see the Jiangsu frozen-food processing workshop.

The photographs show the recorded site or engineering reference. Room classifications, system performance and acceptance requirements are established through the project specification and records.