This 2,500 m² beverage-filling cleanroom project in Jiangsu, China, completed in 2023, shows how production equipment, access platforms and overhead services occupy the room together. Stainless vessels and connected pipework sit within a finished enclosure, with lighting and ceiling interfaces visible above the process area. AILV was responsible for design, on-site installation and system commissioning.
- Location
- Jiangsu, China
- Industry
- Beverage filling
- Project area
- 2,500 m²
- Completed
- 2023
Delivery Responsibilities & Handover
| Project stage | Responsible party |
|---|---|
| Design | AILV |
| On-site installation | AILV |
| System commissioning | AILV |
Confirmed Handover Record Types
- As-built drawings
- Equipment documentation
- Installation inspection records
- System commissioning or test reports
Project Context
The close relationship between equipment and pipe routes makes interface planning important. Production access, cleaning activities and maintenance need to be considered alongside the locations of structural supports, valves and service connections.
Engineering Interfaces to Review
- Review the equipment arrangement and operator routes before setting room boundaries. Confirm installation access and the clearances needed around vessels, platforms and filling-area equipment.
- Coordinate overhead pipework with ceiling modules, lighting and ventilation outlets. Agree support details, inspection access and the responsibility for each service penetration.
- Use the actual cleaning regime to review exposed surfaces and junctions. Define the utility, drainage and equipment-connection requirements with the selected process-equipment suppliers.
Project Photo Album



Plan a Similar Project
For a similar beverage facility, provide the production flow, equipment schedule, utility and cleaning requirements, room drawings and the requested engineering and installation scope.
Explore related engineering solutions · Review project and EPC responsibilities · Discuss your project with AILV
For a food line with a different process layout, see the Jiangsu frozen-food processing workshop.
The photographs show the recorded site or engineering reference. Room classifications, system performance and acceptance requirements are established through the project specification and records.